Downtown Auburn Progress November 2022
On-site work continues on Downtown Auburn's Municipal Complex and infrastructure for the area. Here's the latest from BM&K Construction & Engineering. Regular updates will be provided as the project progresses.
In addition to the new City Hall, the neighborhood that surrounds it is starting to take shape. As a reminder of the details of the Harmony community, click here for a recap of the presentation to Mayor and City Council.
Every step is taken to ensure compliance with the plans and specifications. This includes but is not limited to:
- Soil density testing
- Concrete and materials testing
- Footing and reinforcing inspections
- Pavement testing
In addition to the City of Auburn staff and BM&K supervision, Contour Engineering has been on site to inspect utility installation and earthwork conditions, as well as Onsite Monitoring conducting weekly erosion control inspections.
Recently Completed Activities
Site:
Building:
- Brick and Cast Stone
- Roof Trusses and Decking
- Ice & Water
- Shield Metal Framing
Front View of City Hall
Current Activities
Rear View of City Hall
Site:
- Erosion control
- Curb installation
- Asphalt paving
- Dry utilities
Building:
- Rough in electrical
- Sprinkler piping installation
Upcoming Activities
Site:
- Parking lot and alley paving
- Final platting of lots
- Dumpster enclosure
Full site
Full site
Building:
- Shingle installation
- Cupola installation
- EIFS and thin brick
- Drywall and ceilings
- Storefront installation
For more details about Downtown Auburn's redevelopment activities, subscribe HERE to receive email updates.
|
|
|