Downtown Auburn Progress February 2022

On-site work continues on Downtown Auburn's Municipal Complex and infrastructure for the area. Here's the latest from BM&K Construction & Engineering. Regular updates will be provided as the project progresses.

Every step is taken to ensure compliance with the plans and specifications.  This includes but is not limited to:

  • Soil density testing
  • Concrete and materials testing
  • Footing and reinforcing inspections
  • Pavement testing

In addition to the City of Auburn staff and BM&K supervision, Contour Engineering has been on site to inspect utility installation and earthwork conditions, as well as Onsite Monitoring conducting weekly erosion control inspections.

Recently Completed Activities

Site:

  • 3rd Digging for Pond A

Building:

  • Waterproofing
  • Sally port footing
City Hall

City Hall

Current Activities

Basement

Basement

Site:

  • Retaining Wall at Pond A
  • Pond A
  • Erosion control
  • Stacking for curb and gutter

Building:

  • Procurement
  • Submittals and shop drawings
  • Sally port CMU
6th Street

6th Street

Full Site

Full Site

Upcoming Activities

Site:

  • Dry utilities               
  • Irrigation sleeves
  • Curb installation

Building:

  • Structural steel installation