Downtown Auburn Progress July 2021
On-site work continues on Downtown Auburn's Municipal Complex and infrastructure for the area. Here's the latest from BM&K Construction & Engineering. Regular updates will be provided as the project progresses.
In addition to the City of Auburn staff and BM&K supervision, Contour Engineering has been on site to inspect utility installation and earthwork conditions, as well as Onsite Monitoring conducting weekly erosion control inspections.
Recently Completed Activities
Site:
- Stripping of topsoil
- Mass grading
- Pond C
- Pond B excavation
Building:
- Rebar fabrication
- Cupola shop drawings
Pond B Excavation
Current Activities
Pond C and Parking Lot Retaining Walls
Site:
- Intermediate erosion control
- Storm drainage – 85% complete
- Sanitary sewer – 85% complete
- Retaining walls – Pond B
Building:
- Procurement
- Submittals and shop drawings
- Excavation
Upcoming Activities
Site:
- Pond A
- Water lines – 8/9/2021
- Roadways and swales
Building:
- Foundations
- Exterior finish selections
For more details about Downtown Auburn's redevelopment activities, subscribe HERE to receive email updates.